June 22, 2010 – Allen Pellerin of Systems Integration Group and Michael Woodley, VOL Administrator install the video display in the large booth |
|
June 10, 2010 – George Whittam is gearing-up the lab and testing the booths. |
|
![]() |
| May 18, 2010 - The studio windows are installed. Thank you Paul's Associated Glass Products. | ![]() |
| May 14, 2010 - The donor wall and DLF VO Lab sign are being installed. | |
| |
|
| May 9, 2010 - One step closer. Carpet is installed. | |
| May 7, 2010 - The sound doors are being installed. The ceiling tile is also in place and we have our first coat of paint. | ![]() |
| April 30, 2010 - Painting has begun and will continue next week. Carpet and other finished begin soon. | ![]() |
|
|
|
April 14, 2010 – HVAC silencers are going in place. After a few inspections next week the ceilings will be installed in the booths. |
![]() |
|
March 22, 2010 - Electrical inspection today. Drywall work begins. |
|
|
March 16, 2010 - The electricians are hard at work and the framing is almost complete. |
|
March 9, 2010 - Framing for the walls is underway. HVAC and electrical work continue. |
| March 2, 2010 - Construction meeting, making sure everything is right before things start to go into place. | ![]() |
| February 18, 2010 - Demo was completed. | |
| Future site of the DLF VO Lab, vacant space located adjacent to the Actors Center. | ![]() |